What is a Field Change and how is it authorized?

Prepare for the Construction Quality Management Test. Study with flashcards and multiple-choice questions, complete with hints and explanations. Get ready for success on your USACE exam!

Multiple Choice

What is a Field Change and how is it authorized?

Explanation:
A field change is an on-site modification to the work that addresses conditions or needs found in the field, done within the contract’s approved modification process rather than as a new design from scratch. It is authorized through the contract’s established channels—typically by the Contracting Officer or their designated representatives, such as the Construction Division, or via a field-order mechanism specified in the contract. This ensures the change is properly reviewed, funded, and scheduled, and documented before work proceeds. It’s not something the contractor can do unilaterally, and it’s not always a full design change requiring a new bid.

A field change is an on-site modification to the work that addresses conditions or needs found in the field, done within the contract’s approved modification process rather than as a new design from scratch. It is authorized through the contract’s established channels—typically by the Contracting Officer or their designated representatives, such as the Construction Division, or via a field-order mechanism specified in the contract. This ensures the change is properly reviewed, funded, and scheduled, and documented before work proceeds. It’s not something the contractor can do unilaterally, and it’s not always a full design change requiring a new bid.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy